Northstar Lodge-Hyatt Residence Club

Construction Status: March 29, 2008


Building A


Entry Level

Garage; mechanical and electrical 85% complete

            Fire sprinkler 70% complete

            CMU utility rooms partitions erection  

                                    Lobby/common area steel stud framing complete

Electrical and masonry initiated

Floor 1

            Owners’ lounge and common areas: steel stud framing complete

            Main plumbing rough-in 50% complete

            Electrical 30% complete

            Exterior Gyb started

Floor 2

            Main plumbing rough-in begun

            Pick-up framing

            Exterior Gyb started

Floor 3

            Wall framing complete

            Pick-up framing

            Exterior Gyb started

Floor 4

            Finish framing from gridline 5 to 6

            Trusses erection gridline 1 to 3

            Starting 4-2-08; trusses erection gridline 3 to 5

           

 